A skid foundation uses treated timber runners to carry a framed shed floor. This guide follows one build: prepare a gravel pad, place and level the skids, secure them with screw-in anchors and L brackets, then build the floor.
Is it right for your shed?
Best fit: A framed shed on a prepared, fairly level site.
Advantages
- Long runners spread the floor load.
- A shed with skids may be easier to move.
- The floor sits above wet ground.
Limitations
- Needs a level prepared pad.
- Timber needs room to dry and be inspected.
- Skids alone do not hold down the shed.
Ground layers

Read these layers from the ground up.
- 1
Prepared ground
Remove grass and fix weak soil.
- 2
Ground fabric
Use fabric if needed to keep stone from mixing into soil.
- 3
Compacted gravel pad
Compact crushed stone to make a level pad.
- 4
Treated skids
Set treated runners where the floor plan shows.
- 5
Floor frame and boards
Fasten the framed floor across the runners.
What you need
Get quantities and sizes from your shed plan.
- Ground-contact treated skids sized for the floor plan
- Compacted crushed stone and separator fabric where specified
- Screw-in ground anchors with matching L brackets and compatible timber fasteners
- Floor framing and specified joist-to-skid connectors
- Tape measure, long straightedge, spirit level and the anchor kit's driving tool
Useful planning: choose the shed location and check permit requirements.
Build it step by step
Step 1: Mark the runner positions
Mark the shed footprint and skid lines from the floor plan. Check the doorway position, drainage route and access for installing anchors beside the skids. Locate buried services before digging or driving anchors.

Mark the runner positions and check the layout. Step 2: Prepare the gravel pad
Remove turf, roots and soft soil. Fit separator fabric where specified, then spread and compact crushed stone in layers. Keep the pad level and arrange the surrounding ground so water drains away.

Compact the gravel pad before placing the skids. Step 3: Place the skids
Set ground-contact treated runners on the prepared pad at the spacing shown in the floor plan. Keep them parallel and fully supported along their length. Treat cut ends as the timber supplier directs.

Set the treated skids parallel on the prepared gravel pad. Step 4: Level and align the skids
Check each skid along its length. Lay a straightedge across the runners and check that their tops are level with one another. Adjust and recompact the stone beneath low areas; do not balance the runners on loose wood shims.

Check the runner tops with a straightedge and level before anchoring. Step 5: Anchor the skids
Use screw-in ground anchors with matching L brackets. Fit them while the skids are exposed, before building the floor. The close-up shows one connection to the side of a structural skid.

The spiral holds in soil below the gravel. A bolt and washer connect the anchor head to the L bracket; timber screws fasten the upright face to the skid. One connection is shown, not a complete anchor layout. - At each planned fixing point, screw the anchor vertically into suitable ground beside the skid using the kit's driver. Keep the spiral below the gravel in the soil, and stop if an obstruction prevents the specified installation.
- Fit the L bracket onto the anchor head with its upright face against the side of the skid. Install and tighten the supplied head bolt and washer as the kit directs.
- Use the specified timber screws through the bracket into the structural skid. Drill pilot holes where instructed, tighten the fixings and check that the skid still bears evenly on the pad.
Anchoring is recommended and is required where the shed instructions or local rules specify it. Choose a kit with suitable holding capacity for your soil and shed; check its compatibility with treated timber.
Product example: MIXC screw-in ground anchors with L brackets (Amazon).
Step 6: Build and fasten the floor
Build the floor frame across the anchored skids. Measure both diagonals to check it is square, then fasten the joists to the skids with the connectors specified in the floor plan. Keep the anchor brackets accessible and check the connections before laying the floor deck.

Build the floor after anchoring the skids. The red connectors fasten joists to the runners; the ground-anchor brackets remain below. Anchor positions and quantities follow the shed design.
Mistakes to avoid
- Building the floor before fitting the anchors and their brackets.
- Leaving a skid unsupported or using timber that is not rated for ground contact.
- Fastening a bracket to trim or a gravel border instead of the structural skid.
- Assuming an anchor length or a four-pack automatically suits every shed and soil.
Keep it in good shape
Check the skids for movement and decay, and inspect the anchor heads, brackets and screws for looseness or corrosion. Keep soil and leaves away from the timber. Recheck the connections after significant ground movement or storms.
When to choose a different base
Choose skids for a compatible framed floor on a level prepared base. Choose piers if the ground is too uneven for a practical pad.
Common questions
Can skids sit directly on dirt?
Bare soil holds moisture against timber and can settle. Use the prepared, draining base specified for the shed.
Will an 18-inch screw anchor suit every shed?
No. Length alone does not establish holding capacity. The soil, shed size, wind exposure, bracket connection and number of anchors all matter. Confirm the selected kit's suitability and capacity before using it.
Why anchor before building the floor?
The exposed skids leave room to drive the anchors and fasten the brackets. The floor is then connected to those anchored skids in Step 6.
Further reading
- AWPA: treated wood guidance for homeowners
How to choose treated timber for ground contact.
- ICC: 2024 IRC, Chapter 4 — Foundations
Ground support and frost protection.
- Simpson Strong-Tie: connector holes and fastener types
Use the connector's specified fastener type, size and installation pattern.
- American Wood Council: sill-plate anchorage and the continuous load path
Connect the structure all the way to its foundation; the weakest connection matters.